Construction to begin February 16 on St. Maurice Lane

The City of Natchitoches announces that construction will begin during the week of Feb. 16 on the segment of St. Maurice Lane from Williams Avenue to East Fifth Street.

This work will involve the construction of a new cement-treated base course, along with isolated asphalt pavement patching, followed by placement of new asphaltic concrete surfacing.

During the base reconstruction operation, this section of St. Maurice Lane will be CLOSED to through traffic, but access to adjacent residences will be maintained to the extent possible.

The base reconstruction work is expected to be completed by Friday, Feb. 20, with the subsequent placement of the new asphaltic concrete surfacing anticipated during the week of Feb. 23. Two-way, one-lane traffic will be maintained during the paving operation.

This pavement rehabilitation work is being partially funded by a special appropriation from the Louisiana Legislature during its 2025 regular session. The contractor is Regional Construction, LLC, of Natchitoches.

Questions may be directed to the City Engineer at (318) 357-3877.