A recommended 10% water rate increase and the financial requirements associated with the city’s water plant expansion project were the focus of discussion during the November 23, 2026, Natchitoches City Council pre-council meeting.

Robbie Dickens, representing EisnerAmper on behalf of the Louisiana Office of Community Development and the Water Sector Program, presented the findings of a water rate study conducted for the City of Natchitoches.

Dickens explained that the city’s approximately $14 million water plant expansion project included $5.31 million in grant funding, with the remaining $8.69 million covered through debt service.

As a condition of receiving the grant, the city must maintain a sustainability factor of 1.15 throughout the 10-year grant period. The requirement represents a 15% financial margin above the water system’s break-even point.

The study determined that the city’s sustainability factor was approximately 1.05, below the state’s required threshold.

The study recommended an initial 10% water rate increase, followed by annual adjustments based on the Consumer Price Index, projected at 2.8% in the study. Dickens identified approximately $487,000 in additional debt service coming online during fiscal year 2027 as the primary factor driving the recommended increase.

For residential customers within the city limits, Dickens estimated that a 10% increase would amount to approximately $3 per month, or $36 annually. The actual increase would vary depending on customer classification.

Dickens also explained that delaying implementation of the recommended increase could affect the city’s ability to meet its financial requirements in subsequent years.

Council members questioned whether the increase could be distributed differently among residential, commercial and industrial customers to reduce the financial burden on residents already facing utility expenses. Dickens explained that the city has the authority to determine how the increase is distributed among customer classifications, provided the additional revenue is sufficient to meet the required sustainability factor. He noted that reducing or eliminating an increase for one customer classification would require other classifications to absorb a larger portion of the increase.

Dickens encouraged officials to use the financial model provided through the rate study to evaluate potential changes and ensure they would generate the necessary revenue.

Discussion also addressed whether the city could transfer funds from its electric utility to supplement water operations. Dickens explained that such transfers have been rejected by the Water Sector Program, which seeks to ensure that individual utility systems are financially sustainable.

Mayor Ronnie Williams Jr. indicated that the administration has been communicating with state officials regarding potential alternatives to an immediate water rate increase.

Dickens noted that some municipalities have used dedicated sales tax revenue to address financial shortfalls. Such arrangements would require state approval and specific language ensuring that the revenue is dedicated to maintaining the required sustainability factor. Failure to meet the grant requirements could result in the city being required to return approximately $5.31 million in grant funding, leaving the city responsible for covering the resulting funding gap in the ongoing water plant expansion project.

The discussion took place before the regularly scheduled 5:30 p.m. City Council meeting. No formal action was taken, and no water rate increase was approved.